Seajacks Scylla Loading First Walney Extension Turbine Components

Seajacks’ wind farm installation vessel, Seajacks Scylla, has arrived in Belfast and is being loaded with the first batch of turbine components to be installed at the 659MW Walney Extension offshore wind farm, DONG Energy told Offshore WIND.

“Seajacks Scylla arrived at the Walney Extension feeding harbour in Belfast on time and loading is progressing as planned. We expect installation of the first MHI Vestas 8.25 MW turbine to begin over the coming week,” Andrew Cotterell, Walney Extension programme director, said.

Walney Extension will consist of 40 8.25MW MHI Vestas and 47 7MW Siemens wind turbines, as well as two offshore substations, installed some 19 kilometres off the Cumbrian coast. Seajacks Scylla will install all 87 wind turbine units at the wind farm.

The turbine components and foundations, which are currently being installed, are being stored in Belfast and the construction is coordinated from the port of Barrow in Furness.

When fully commissioned in 2019, Walney Extension will become the world’s largest operating offshore wind farm.

Sourced: Offshorewind.biz

Gallery

wind_week-33 wind_week-57 wind_week-99 wind_week-8 Offshore Wind Meets... Conference at OrbisEnergy. Pic by TMS Media Ltd OrbisEnergy Boardroom Networking Reception

Upcoming Events

The Team

Katie Snell

Having worked within the property department for 9 years, I have had the pleasure of working within the majority of the Nwes sites in the Norfolk and Waveney area. For the last 2.5 years I have been based at OrbisEnergy and more recently as Senior Coordinator overlooking the renewable hub and team.

Devon Mills

Devon has joined the team at OrbisEnergy as an Administration Coordinator in November 2014 and more recently a Centre Coordinator in January 2016. Having previously worked within various customer service roles she is pleased to be able to apply her skills and knowledge to her position at OrbisEnergy.

She is keen to build a strong understanding within the Offshore Renewable industry, whilst being able to develop a good mind for business and sales.

Johnathan Reynolds

Johnathan is responsible for all aspects of business and supply chain development for the flagship innovation and incubation centre for offshore renewables in the east of England, OrbisEnergy.

Matthew Holden

Matt’s role is Technical Support Manager, his main duty is leading the European Clusters for Offshore Wind Servicing Project (ECOWindS, www.ecowinds.eu) on behalf of Nwes. In addition to ECOWindS Matt’s role is provide support for the property team and to carry out specific project work.

John Balch

John is Managing Director of Nautilus, Director of Nwes and Hub Director of OrbisEnergy and Beacon Innovation Centre. He is a mechanical engineer and has broad experience gained over 40 years in the international offshore industry.

  • loading tweets...